This is a job we have lined up.
Need to cut off the complete overhang. ![]() No scaffolding allowed from ground up. No noise, no vibration on structure, no disturbance to guests and NOTHING is allowed to fall. Hilton Hotel - Park Lane London ![]() ![]() |
#2
|
|||
|
|||
![]()
What's the time frame and copies of RA and HA Clive
|
#3
|
||||
|
||||
![]()
But I know a pie key who will take the hand rail
|
#4
|
||||
|
||||
![]()
Reminds me of my window cleaning days and bosons chairs !
__________________
Eat, Sleep, Race , Repeat |
#5
|
||||
|
||||
![]()
Cantilever scaffold??
You would even get me up there let along work ![]()
__________________
Keep it on the black stuff and leave the pit boards alone ![]() |
#6
|
|||
|
|||
![]()
You been drinking E? Sod that Mr fudge no way. Whatever there paying its not enough
![]() |
#7
|
||||
|
||||
![]()
do you employ the disabled,cash in hand
![]() o yes and petrol |
#8
|
||||
|
||||
![]()
Iv got a friend who's qualified to do that sort of scaffold if you need help could ask for you??
__________________
"We're here for a good time, not a long time...." Colin McRae MBE 1968-2007" |
#9
|
||||
|
||||
![]()
LOL
Scooby Hoo I haven't read the MSRA (Method Statement / Risk Assessment) and there is a good reason why. I haven't written it yet ![]() I don't have the luxuries of reading how to do any of our contracts. I compile all documents myself Hugh and the timescale will be what I tell them it will be. I'm still on the case and haven't worked out duration yet but a guess would be 5 days / 2 men to complete. I don't receive any H&S issues either but they will be part of my MSRA. No generic MSRA's here mate, I have to write a complete "Section 10 MSRA) for each job. I need to assess everything that can wrong, then produce 4 grades of "how likely". ranging from unlikely (1 point) to possibly which is 4 points. I then need to suggest "how bad" things will be regarding failures ranging from Minor (which is 1 point) to Critical which is 4 points. If the total points of what can go wrong and how bad total 3 or more I then need to come up with a plan explaining how we intend to tackle the problem in a safe manner. Needless to say EVERYTHING ends up with more than 3 points. My completed documents are then sent to the main contractor, H&S Officers, Structural Engineers and in some cases suppliers. I often hear we were not the cheapest quote but always hear we are the most thorough and that's why we are awarded a large % of what I quote for. |
#10
|
|||
|
|||
![]()
Oh, the joys of RAMS , I'm iosh certified as have to write RAMS all the fookin time . H&S what a joy it is .
|
![]() |