View Single Post
  #1  
Old 21-11-2010, 09:00 PM
Scott.T's Avatar
Scott.T Scott.T is offline
Admin, Meets/Events Organiser.... formerly known as SilverSurfer
 
Join Date: Sep 2008
Location: Hastings, East Sussex
Posts: 9,485
Default A bit of manual Labour

Thought I'd have a go at a bit of manual labour, to work off a few calories on the run up to Christmas.

Got the offer of a Conservatory at a good price, the downside was I needed to prepare for it's arrival at the onset of winter.

Never seriously laid a brick before in my life...but hey the internet's great.
Watched a few YouTube clips and thought how hard could it be......

Late September/Early October
A bit of digging out of the old Patio for some footings.
Lots of old concrete found underneath existing patio. Looked to be original patio groundwork, in some places about 6 inches thick
Smashed through to soil using heavy solid iron bar.
Wrists suffered a bit of RSI for the following weeks (should of hired a Kango).

Dug down approx 22 inches accross Patio and between 22 inches and 18 inches accross front lawn.




Early October
Borrowed a mixer of RobEvo5 (thanks Rob) and spent a whole day shifting 2 Tonnes of Ballast, Mixing and pouring into trench accross front Lawn.
Couldn't beleive it took all day.

Following weekend, spent another whole day shiftng, mixing and pouring another 2 Tonnes into remaining stepped trenches.

Mid/Late October
Concrete footings set and started Block work upto Damp Course (Block work will be rendered over once complete).




Early November
Hardcore Backfill
1 Tonne (50mm depth) of Building sand levelled and compacted
Waterproof Membrane
50mm Celotex Floor insulation
Waterproof Membrane
2 tonnes of 100mm Concrete Slab poured and levelled upto floor level

'WARNING' wet concrete burns if exposed too, for long periods.
I was mixing, pouring and leveling from 0830 until 1500, non stop. Getting wet from the concrete and also the drizzle.
Clothes and gloves got soaked and I ended up with alkaline/acid burns to hands and knee's.
This stopped all work for 1 week and very painful.

Mid November
Commenced Brickwork, matched too house. 8 courses required in Total
Commenced inner Block Wall/Cavity Wall
(pics to follow)

Last edited by Scott.T; 21-11-2010 at 09:32 PM.
Reply With Quote